The pipeline will pump as much gas as the Habshan 5 mega project can process.
The pipeline will pump as much gas as the Habshan 5 mega project can process.

RELATED ARTICLES: Habshan-Fujairah pipeline operational | Habshan 5 mega-project 17 months ahead of schedule | UAE contractor wins $450m Abu Dhabi pipeline deal

RELATED ARTICLES: Habshan-Fujairah pipeline operational | Habshan 5 mega-project 17 months ahead of schedule | UAE contractor wins $450m Abu Dhabi pipeline deal

Dodsal Engineering & Construction has won a $764m contract to install two gas pipelines between Habshan and the Khalifa Port and Industrial Zone (KPIZ) in Taweelah, Abu Dhabi.

The Abu Dhabi Gas Industries (GASCO) pipe network will cover a total of 297km, travelling from Habshan to Maqta and then onto Taweelah.

The contract scope covers the engineering, procurement and construction (EPC) of the two 52-inch diameter pipelines  -  a requisite for the ultimate transportation of up to 28 million m3 a day.

The Habshan 5 mega-project, which will feed gas to the pipeline, was 90% complete in June, 17 months early.

GASCO's project is schduled to be completed by June 2015.

 