Articles
Companies

Home / Site visit: The One at Jumeirah Village Circle

Site visit: The One at Jumeirah Village Circle

by Jochebed Menon on Jan 7, 2017




The One is a 44-storey, four-star hotel located in Jumeirah Village Circle (JVC), which is scheduled to complete in September 2018.

Currently under construction, The One at Jumeirah Village Circle is being developed by First Group and will be operated by Wyndham Hotel Group under the Ramada Plaza brand.

Dubai-based First Group has several developments on the way, including three other Ones. Namely, The One Hotel at Business Bay, The One at Jumeirah Village Triangle, and The One Dubai Marina.

The developer’s other hospitality projects include Wyndham Dubai Marina, Sky Central Hotel, Metro Central Hotel Apartments, Grand Central Hotel Apartments, and First Central Hotel Apartments, all in Barsha.

The One at Jumeirah Village Circle is located at the apex of two of Dubai’s main road arteries, Al Khail Road and Sheikh Mohammed Bin Zayed Road, alongside a number of other hospitality projects in the neighbourhood.

This 496-key hotel will have two speciality restaurants and an all-day-dining eatery, along with a swimming pool, gymnasium, steam rooms, and a sun deck.

Construction work has reached parking podium two as of December 2016. When Construction Week visited the site, shuttering was taking place on the roof of podium two.

Adnan Nalwala, executive director of Akar Technical Services, says: “We are excited about developing a premier hotel property in Dubai. This development further strengthens our portfolio of hotels in the Middle East, adding a new dimension to the overall expansion of our brand.

“Aligned with UAE’s Vision 2021, Akar is deeply committed to developing real estate projects that add value to the long-term strategic development of country.”

Main contractor, China Railway 18th Bureau Group, was awarded the tender in January 2016, and the contract was awarded in April. The mechanical, electrical, and plumbing (MEP) works contract was awarded to Akar Technical Services in August 2016.

Speaking to Construction Week, Akar’s project manager onsite, M Selvaraj, says: “Work on the main structure began in June 2016 and, right now, we’ve completed the structure for podium two. The construction casting is completed up to podium two.”

He adds that construction on the main structure will be completed by January 2018.

The building will have four levels of parking. The ground floor and basement will consist of a hotel reception, mechanical equipment room, staff dining, utility quarters, kitchens, a storage room, and service rooms.

“The structure from [the] ground floor until the fourth floor is a conventional slab structure, and [the] fifth floor and upwards will have a post tensioning slab,” Selvaraj explains.

Zhou Lin, project manager from China Railway 18th Bureau Group, says that the hotel will have 160 parking bays in the four podiums. On the MEP front, Akar’s Selvaraj continues: “The first fix – such as the containments, which are the concealed works within the concrete – is ongoing. The second fix – making the supports and installing the pipes and taps – is expected to be done by February 2017.”

Enabling and piling work was carried out by Turkish firm, Zetas Zemin Teknolojisi AS, while ground breaking took place in December 2015. Lin says: “We started working on the foundation in July 2016, following which, work began on full scale with a workforce of 200 labourers.”



Advertisement



RELATED ARTICLES



Articles
Companies