Face to Face: The tall order of building the Burj

by CW Guest Columnist on Jan 31, 2009

  Be the first to comment
RSS Feeds Print this page

Senior mechanical engineer Alastair Mitchell.
Senior mechanical engineer Alastair Mitchell.

What is your company’s role in the Burj Dubai project?
Hyder Consulting Middle East Ltd is the architect of record (AOR) and construction supervision consultant for Burj Dubai project.

The primary challenges involved with MEP system installation works in Burj Dubai are the high pressures – which is what differentiates this project from other projects. It means we have to look outside the construction industry for some of the materials and skills required to construct these services.

We have to be much more careful with quality control and pay attention to procedures that are typical in other industries, but not standard within the construction industry.

Story continues below
Advertisement

FEATURED COMMENT

Please click here to comment on this article

There is also an element of education and training involved with this. There is also a large amount of supervision, in this case to make sure that the contractors take adequate responsibility, and implement the QAQC procedures that are necessary to ensure equipment is installed correctly.
 
The MEP contractors on the project employed a third-party consultant to do a very extensive stress analysis, expansion and contraction and anchor load analysis for all the main piped systems within the project. The analysis of the reports generated by these studies was then incorporated into the contractors shop drawings.

Hyder Consulting site team had to make sure that the contractor re-visited everything on site before making the services live.

How is this project different?
Burj Dubai is a special project as we are creating the tallest building in the world. Due to the scale of the project the main contractor and the MEP contractors for the project have had to form joint ventures.

Joint ventures have in my experience led to problems in the past but we are pleased to say that in this case at a site level the contractors have worked well together to construct what is a complex and technically challenging project.    
 
Was it an issue to co-ordinate between so many contractors for a large project such as Burj Dubai?
It is a complex building. Because it is so big, the work packages have to be split up into different sub-packages. We have one MEP contractor that does the whole project. But we have four fit-out contractors doing different zones of the building, so one has to deal with different people.

We co-ordinate something to fit into one zone of the building, then we have to do it all over again and fit it into the next zone of the building with a new set of people. This process is time consuming, but it is something that cannot be avoided.
 
What was unique about this project?
Burj Dubai is what brought me to Dubai. It was an opportunity to work on what is arguably the most amazing construction project in the world at this point in time. With this economic downturn the chances are it will remain the tallest building in the world for quite a few years to come. Some taller buildings have been announced, but I am not sure how many of them will continue or how soon they will they begin to be built – if ever.

It has been great to work in a project where you don’t have to keep justifying yourself. The developer has been extremely understanding to our need to use the specified high-quality products and materials. There has been little interference and the best designers, consultants and contractors have been employed on the project.

If we were halfway into the contract in these difficult times the  possibility is that the client would come have come to us to ask how we could do it quicker and cheaper. But this has not happened and high standards are being maintained throughout the project. 
 
Have you used a different approach to the MEP works in Burj Dubai?
The technologies we have used are quite traditional. We are just stretching the way they are applied. The pressures, the height and size of the main piped system risers are the difference. There is probably no other building in the world that has 300m long vertical service risers.

There are other industries which do it frequently, but in the construction industry it is unusual. We thought about many things even down to the method of welding riser pipes together to ensure better quality welds, these things are not always thought about in other construction projects.
 




COMMENTS

Name *
Email *
City
Country
Subject: *
Comments: *
Math Question: *
Solve this simple math problem
and enter the result. E.g. for 1+3, enter 4.
Refresh the image if not clear
Remember me on this computer



NEWSLETTER SUBSCRIPTION
Email:



Arabian Supply Chain Middle East
Hotelier Middle East
Digital Production Middle East
Arabian Oil and Gas Middle East
Construction Week Online - India
Utilities middle east\
Hotelier India
LinkedIn
CWO dotcom



Articles
Companies
ITP.com
Ahlan.ae Masala.ae Ahlanlive.com ArabianBusiness.com ArabianBusiness.com/Arabic ArabianBusiness.com/Jobs ArabianBusiness.com/Property ArabianOilandGas.com ArabianSupplyChain.com ArabianTravelDirectory.com ConstructionWeekOnline.com ConstructionWeekOnline.com DigitalProductionME.com Grazia.ae HotelierMiddleEast.com ITP.net TimeOutAbuDhabi.com TimeOutDubai.com TimeOutTickets.com Utilities-ME.com VivaMagazine.ae commsmea.com designmena.com