Amber Residence, Dubai World Central
[More Images]
Interview with Damac's CEO Peter Riddoch
This week Damac announced its plans for new projects worth US $544 million (AED2 billion), eight of which will be awarded by the end of this year. Construction Week finds out what they are and when to expect tender documents.
1- DAMAC Heights, Dubai Marina
Description: This is a 90-storey residential tower at Dubai Marina featuring one-bedroom units up to duplexes and penthouse apartments.
Status: Enabling works contract award expected in Q4 2009.
Tender: Enabling works contract expected to be tendered this week, the main contract tender is due in October, while the main contract award can be expected in early 2010.
Story continues below

Advertisement
|  |
|
2- Amber Residence, Dubai World Central
Description: Ten-storey residential complex located at Dubai World Central residential city. The development will have retail outlets on the ground floor and feature studio, one and two bedroom units.
Status: Enabling works have been completed by National Piling and the main contractor is due to be appointed in Q3 2009.
Tender: Main contract expected to be tendered in June.
3- Park Central
Description: This is a 17-storey project designed to give views across the lake from three sides of the tower. It has parking on four levels.
Status: Enabling works have been completed by Al Habtoor STFA and the main contract is due to be awarded in Q3 2009.
Tender: Main contract expected to be tendered in June.