Project Management Group (PMG) has handed over phase one of the US $300 million Jumeirah Business Centre Towers to developer Al Fajer.
PMG claims that its management of the project has saved the developer around $16 million.
"We were brought in to address delays which had plagued the project due to the absence of a professional project management firm and to ensure the cost and quality would be up to the standard required by the development firm," said PMG executive partner Ahmed K. Awad.

![]()
PMG efforts included retendering the project's nominated subcontracts, which successfully trimmed down the final cost for each tower. Construction was stepped up to a rate where a total of 200 floor slabs were poured over a period of 10 months, reaching a 4-day pour cycle per floor and cutting construction time in half.