The big money cycle

by Ben Roberts on Jul 18, 2010

  Be the first to comment
RSS Feeds Print this page

Design changes to Dubai's Palm Jumeirah had complicated cost issues, says a project manager.
Design changes to Dubai's Palm Jumeirah had complicated cost issues, says a project manager.

He says this milestone percentage of completion can complicate the checks and balances. “Instead of getting lost in details of the stages of work reached, we pay at the end of a project, and at the beginning – but not in between,” he says.

The second issue surrounds changes to the contract, which may have started as a lump sum contract, but has been amended into a re-measured contract. This is linked to the third issue, in which, after a contract has been signed, but aspects of the design are altered by different counterparties, the resulting changes may affect the overall cost.

Elayache recounts his time as a project manager on the Palm Jumeirah. “When we started it was a lump sum project and we said to the developer to ‘go ahead with the requirements’. Then people in the developer started to change bits of
the design.

 

Story continues below
Advertisement

FEATURED COMMENT

Please click here to comment on this article

“I got AED100 million from Nakheel and I had to fight for my contractor. People from the developer said ‘we can improve here’ and thought they could get away with it.”

The fourth issue is the difficulty in obtaining the right information. Elayache explains that it is often a challenge to get a thorough overall view of a project even aside from monetary issues, which is why his firm advocates the use of value engineers.

“I hired three project control companies as I wanted to get a good picture and we had bonuses linked to performance. With the traditional way of construction it’s difficult to control work progress.”

The last issue regards the processing of costs. To maintain a clear separation of the different types of outflows, Elayache recommends logging all overheads at the beginning of the contract, with costs for specific work undertaking of the contract later.

This allows changes to the design if needed. The alternative is to calculate overheads with each specific work activity, which can quickly complicate matters and be difficult to calculate, especially when designs are changed and this will affect the work needed and the resulting overheads for that work.

Project payment disputes
Money flow between developers, contractors and investors has been a critical discussion point amid the economic downturn on the back of high-profile legal cases.

One such aspect of this is the introduction and use of the ‘escrow’ payment method – essentially an independent account into which investors would pay funds with payments released to the developer within an agreed structure.

Walid Jaafar, partner at Fichte&Co, a Dubai based law firm, says that although the concept has been around for some time, it is new to the real estate market in the region and coincided with the high-growth years in the Dubai market.

“When the escrow account system was created in the real estate industry all developers rushed to their banks to meet a deadline to set them up,” he says.

“The escrow system means money is paid into an independent account, and when a milestone is reached, a consultant will verify the payment to the developer. If a project is on hold, the developer is obliged to return money to investors.”

However, Jaafar says there have been cases in which when investors seek to reclaim funds, the money has been taken out by the developer and it is empty. The money should be able to be traced, he says, but the legal representatives cannot go to the bank to seek amends.

Court proceedings usually result from the non-completion of a project or when the developer has defaulted – often the two circumstances are linked. But Jaafar adds that developers would defend themselves when the original contract does not state a specific date for completion.

“For a lot of agreements the time in which it should be completed is essentially forever. Some developers will be working under a specific completion date, but in other cases a contract is signed in 2007 with a deadline of sometime in 2012, giving them five years.

“Legally we would say that this is an unbalanced contract – all the buyer can do is sue the company, which can take a long time with the buyer incurring
more costs.”

Jaafar believes that on the back of high-profile lawsuits and a deflated property market compared with 2007, there will be closer scrutiny of contracts.

“I think people have learned their lesson with regards contracts,” he says.




COMMENTS

Name *
Email *
City
Country
Subject: *
Comments: *
Math Question: *
Solve this simple math problem
and enter the result. E.g. for 1+3, enter 4.
Refresh the image if not clear
Remember me on this computer



NEWSLETTER SUBSCRIPTION
Email:



Arabian Supply Chain Middle East
Hotelier Middle East
Digital Production Middle East
Arabian Oil and Gas Middle East
Construction Week Online - India
Utilities middle east\
Hotelier India
LinkedIn
CWO dotcom

RELATED ARTICLES





Articles
Companies
ITP.com
Ahlan.ae Masala.ae Ahlanlive.com ArabianBusiness.com ArabianBusiness.com/Arabic ArabianBusiness.com/Jobs ArabianBusiness.com/Property ArabianOilandGas.com ArabianSupplyChain.com ArabianTravelDirectory.com ConstructionWeekOnline.com ConstructionWeekOnline.com DigitalProductionME.com Grazia.ae HotelierMiddleEast.com ITP.net TimeOutAbuDhabi.com TimeOutDubai.com TimeOutTickets.com Utilities-ME.com VivaMagazine.ae commsmea.com designmena.com