Site Visit: Back to school

by Gerhard Hope on Aug 4, 2010

  Be the first to comment
RSS Feeds Print this page

A major challenge on the project has been overall co-ordination of the MEP works
A major challenge on the project has been overall co-ordination of the MEP works

RELATED ARTICLES: DSI lands $21.8m deals in Kuwait, Qatar and OmanDSI wins AED140m Qatar MEP contractAmerican University of Sharjah to invest in landscape study

The AED85 million MEP works contract for general contractor Al Ahmadiah Aktor is being undertaken by Drake & Scull International PJSC (DSI). The project manager is DG Jones & Partners, while the design was by RMJM, an architectural firm that specialises in school design.

The design of the new ASD campus has incorporated the latest sustainable trends, with wind patterns and orientation being considered carefully in terms of the direction and placement of structures. In order to conserve energy, the buildings have been designed so that windows are not in direct sunlight, while special shadings have been designed.

DSI Manager of Projects Ahmed Shaker explains that DSI’s works are progressing very well as per the MEP works schedule. The anticipated opening date of the new ASD campus is 14 September to coincide with the new academic year.

Story continues below
Advertisement

FEATURED COMMENT

Please click here to comment on this article

“The main challenges have been the timeframe and complexity of design,” says Shaker. “Schools and hospitals, for example, cannot be compared to commercial projects like apartment buildings. They are far more complex structures that require careful integration of multiple requirements.”

DSI is not unfamiliar with the rigours and exigencies of educational facilities, with Zayed University in Dubai and KAUST in Saudi Arabia already under its belt as top-notch achievements in this specialised field.

ASD superintendent Dr. Harold Fleetham says that, while there are 973 students at ASD’s existing campus, the new campus has been designed to cater for 1 600 students, with enrolment taking place in stages.

The first year will see approximately 1 400 students enrolled, with the balance to be introduced later. The new campus is divided into two separate schools, namely elementary (comprising kindergarten to Grade 5) and secondary (comprising middle school and high school).

Shaker says the project site is 92 903 square metres, which equates to a million square feet. The total gross internal floor area is 58 622 square metres. In comparison, the existing campus is 31 424 square metres. Designed to withstand the inclement UAE weather, the new ASD campus is also expected to set a benchmark for educational facilities in the region in terms of quality, aesthetics and technology.




COMMENTS

Name *
Email *
City
Country
Subject: *
Comments: *
Math Question: *
Solve this simple math problem
and enter the result. E.g. for 1+3, enter 4.
Refresh the image if not clear
Remember me on this computer



NEWSLETTER SUBSCRIPTION
Email:



Arabian Supply Chain Middle East
Hotelier Middle East
Digital Production Middle East
Arabian Oil and Gas Middle East
Construction Week Online - India
Utilities middle east\
Hotelier India
LinkedIn
CWO dotcom

RELATED ARTICLES





Articles
Companies
ITP.com
Ahlan.ae Masala.ae Ahlanlive.com ArabianBusiness.com ArabianBusiness.com/Arabic ArabianBusiness.com/Jobs ArabianBusiness.com/Property ArabianOilandGas.com ArabianSupplyChain.com ArabianTravelDirectory.com ConstructionWeekOnline.com ConstructionWeekOnline.com DigitalProductionME.com Grazia.ae HotelierMiddleEast.com ITP.net TimeOutAbuDhabi.com TimeOutDubai.com TimeOutTickets.com Utilities-ME.com VivaMagazine.ae commsmea.com designmena.com