The pouring of 23 columns for Tower 1 has been completed on the B1 level and shuttering work is in progress. Rebar cleaning work for columns is also underway along with waterproofing work on top of the raft sides. The Jump form outer shutter opening and cleaning work is also currently underway. Email to friend