| Status | | | Construction | |
| Scope | | | The project calls for the upgrading of 6.5 kilometres of roads and the construction of five interchanges. The work will also involve the design and construction of a storm water micro-tunnel alongside the Dukhan Highway. | |
| Schedule | | | The joint venture of Saudi Binladin Group and the local Qatari Diar was awarded the main construction contract. The work is scheduled to begin in June 2011. Project duration is 42 months. | |
| Remark | | | ||