Haramain High Speed Rail Project - Phase 1Last Updated: Jan 7, 2010 |
|||
| Client | | | Saudi Railway Organization (SRO) |
Actual Value: 1.9bn USD
Haramain High Speed Rail Project. |
| Contractors | | |
Main Contractor: Al Rajhi consortium Main Contractor: Changchun Railway Vehicles Co. (Vehicles Supplier) Main Contractor: China Railway Engineering Corporation |
|
| Consultants | | |
Main Consultant: Dar Al Handasa Consultants Main Consultant: Getinsa Main Consultant: Scott Wilson Co Ltd (Project Manager) |
|
| Country | | | Saudi Arabia | |
| Category | | | Infrastructure | |
| Project Type | | | Others | |
| Project Duration | | | From: Q2 2009 Actual To: Q1 2013 Actual |
|
| Status | | | Construction | |
| Scope | | | Haramain High Speed Rail Project is a rail link project will connect Makkah and Madina via Jeddah. The railway will be a high speed electrified passenger double line between Makkah, Jeddah and Madina. The speed of the train is around 360 km/h. The design, construction, operation, maintenance of HHR shall be executed in two phases. | |
| Schedule | | | Scott Wilson Co Ltd has won a US$ 23.1 million contract to provide project management support to the Haramain High Speed Rail Project. | |
| Remark | | | The project will also connect Jeddah Airport with the other places. | |