Roads Work in Al-Quoz AreaLast Updated: Mar 4, 2009 |
|||
| Client | | | Roads & Transport Authority (RTA) |
Actual Value: 235m USD |
| Contractors | | |
Main Contractor: Gunal Construction Trading & Industry |
|
| Country | | | United Arab Emirates | |
| Category | | | Infrastructure | |
| Project Type | | | Roads Construction | |
| Project Duration | | | From: Q3 2008 Actual To: Q3 2010 Actual |
|
| Status | | | Construction | |
| Scope | | | The project calls for construction of two multi-level interchanges to replace two roundabouts in Al-Quoz area. | |
| Schedule | | | Gunal Construction Trading & Industry was awarded the main construction contract in July 2008. Construction is in progress and expected to be completed in 3rd quarter of 2010. | |
| Remark | | | ||