| Status | | | Construction | |
| Scope | | | The works are divided to 3 parts; Part 1 & 2 includes construction of 5,250m of two lane dual carriageways (32m to 64m corridor), and 37,580m of one lane single carriage ways (16m to 24m corridor) while Part 3 includes construction of around 11.4km of one lane single carriageways (16m to 24m corridor). The Site is located approximately 10km to the northwest, outside the town centre of Doha. | |
| Schedule | | | A joint venture of Burhan Int\'l & ITC was awarded the main construction contract in February 2010. | |
| Remark | | | Contract No. "PWA/GTC/002/06-07/R1" | |