Built to inform

Sign up for the daily newsletters

No, Thank you

Az-Zour North power project now 65% complete

Kuwait's $1.4bn independent power and water plant to be up and running by end of 2015

Photo for illustrative purposes
Photo for illustrative purposes

Shamal Az-Zour Al Oula said that work at the plant, the first independent power and water plant (IPWP) in Kuwait, is currently around 65% complete.

Five of the plant's seven turbines have already been installed - each of which is capable of generating around 226 watts. The last two turbines are set to be installed in June, when it will begin initial generation. The complex is expected to generate 1,500MW of power and 480,000m3 of desalinated water per day once fully operational by the end of the year.

The power plant is being built by main contractor Hyundai Heavy Industries, while Sidem is responsible for the desalination element. They are delivering the project on behalf of Shamal Az-Zour Al Oula, which is a joint venture between France's GDF Suez, Japan's Sumitomo Corporation and Kuwait's Abdullah Hamad Al Sagar & Brothers. They have a deal in place to supply Kuwait's government with electricity and water for 40 years.

The firm said that 4,200 people have worked on its construction, and that by November last year more than 7mn man-hours had been completed at the project without a single accident taking place.

 

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week - Issue 761
Mar 21, 2020