Who's building Qatar 2022 FIFA World Cup stadiums?

A look at the construction firms behind Qatar's five planned stadiums for 2022 FIFA World Cup

Al Wakrah Stadium.
Al Wakrah Stadium.
Al Bayt Stadium.
Al Bayt Stadium.
Khalifa International Stadium.
Khalifa International Stadium.
Qatar Foundation Stadium.
Qatar Foundation Stadium.
Al Rayyan Stadium.
Al Rayyan Stadium.

Earlier this week, Qatar's Supreme Committee for Delivery and Legacy (SCDL) announced it will decide how many stadiums it intends to host the 2022 FIFA World Cup in, by the end of this year. 

In the meantime, Construction Week looks at the contracting and consulting firms lined up to construct the five stadiums Qatari organisers have announced so far.

The stadiums are listed in the order they were announced, based on a report by newswire Reuters

Al Wakrah Stadium

Location: Al Wakrah

Construction start date: Third quarter (Q3) 2015

Estimated completion: Q1 2018

Project Management Consultant: KEO International Consultants

Main Construction Contractor: To be decided

Designer and Engineering Consultants: AECOM

Architect: Zaha Hadid Architects

Al Bayt Stadium

Location: Al Khor Municipality

Construction start date: Q4 2015

Estimated completion: Q3 2018

Project Management Consultant: Projacs

Main Construction Contractor: Joint venture of Galfar Al Misnad, Salini Impregilo Group and Cimolai.

Designer and Engineering Consultants: Dar Al-Handasah

Khalifa International Stadium

 

Location: Al Rayyan municipality

Construction start date: Q2 2014

Estimated completion: Q2 2017

Project Management Consultant: Projacs

Main Construction Contractor: Joint venture between Midmac Contracting and Six Construct

Designer and Engineering Consultants: Dar Al-Handasah

Qatar Foundation Stadium

Location: Education City, Al Rayyan Municipality

Construction Start Date: Q2 2013

Estimated Completion: Q3 2019

Project Management Consultant: ASTAD Project Management

Main Construction Contractor: To be decided

Designer and Engineering Consultants: FIA Fenwick Iribarren Architects

Al Rayyan Stadium

Location: Al Rayyan Municipality

Construction start date: Q1 2016

Estimated completion: Q1 2019

Project Management Consultant: AECOM

Main Construction Contractor: To be decided

Designer and Engineering Consultants: Ramboll and Pattern 

 

 

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week - Issue 765
Jun 29, 2020