Saudi Kingdom Holding's 1km Jeddah Tower 20% done

Up to 37 floors of the 1km-tall Jeddah Tower, formerly known as Kingdom Tower, are ready, development group Kingdom Holding reportedly said

Up to 37 floors of Jeddah Tower have been completed.
Up to 37 floors of Jeddah Tower have been completed.

Saudi Arabia's 1km Jeddah Tower, formerly known as Kingdom Tower, is reportedly over 20% complete. 

Kingdom Holding, which owns a third of the tower's developer, Jeddah Economic Company (JEC), said in a statement that 37 floors of the tower have been built. 

The building, upon its launch in 2018, will be the world's tallest. 

According to newswire Zawya, the Council on Tall Buildings and Urban Habitat (CTBUH) has previously estimated the tower will comprise 167 floors. 

JEC has not formally announced the total number of floors in the structure. 

However, CTBUH's estimations of the tower's total floors means it is currently 22% complete. 

This announcement came as JEC established the Alinma Jeddah Economic City Fund, following the procurement of sharia-compliant financing worth $959.9m (SAR3.6bn) from Alinma Bank in December. 

Remarking on the development, Mounib Hammoud, CEO of JEC, said: "With financing in place, we are now on our way to achieve our set goals and to complete building Jeddah Tower and the infrastructure of Jeddah Economic City as per the five year plan developed by Jeddah Economic Company."

 

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week Middle East 11th Jan 2020
Jan 16, 2020