Glass delivery times double

Soaring demand for glass products in the construction industry has meant delivery lead times have more than doubled over the last year, to 10 weeks.

Soaring demand for glass products in the construction industry has meant delivery lead times have more than doubled over the last year, to 10 weeks.

“There is no way in a million years we can meet demand here. We are struggling to do what we can with what we have,” said Arthur Millwood, technical and training manager, Emirates Glass, one of the big four industrial suppliers of glass in Dubai.

He added: “Typical delivery times now are running to 10 weeks which is much more than normal. A year ago we were talking four weeks.

”According to Millwood, the continued expansion, which he believes is unprecedented on a global scale, is asking too much of local glass manufacturers.

 

Most popular

Awards

CW Oman Awards 2020: Meet the winners
A round of the thirteen winning names at the Construction Week Oman Awards 2020 that

Conferences

Leaders UAE 2020: Building a sustainable, 'resilient' infra
AESG’s Phillipa Grant, Burohappold’s Farah Naz, and Samana's Imran Farooq on a sustainable built environment
CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this

Latest Issue

Construction Week - Issue 767
Sep 01, 2020