Built to inform

Sign up for the daily newsletters

No, Thank you

Construction on Barakah power plant 75% complete

Unit 3 and 4 at the Barakah Nuclear Energy Plant is 50% complete with the plant set for a 2020 completion

This image is for representational purposes only.
This image is for representational purposes only.

Construction work on Emirates Nuclear Energy Corporation’s (ENEC) Units 3 and 4 at the Barakah Nuclear Energy Plant is 50% complete with 75% of the overall construction completed.

The construction progress include the setting of Unit 3’s Reactor Containment Building (RCB) Liner Dome section and effectively installing the roof of the structure which now houses the Reactor Vessel (RV).

Further, the completion of Unit 4’s Turbine Generator Operating Deck and the setting of the last Reactor Containment Liner Plate Rings mark important progress for the units, Saudi Gazette reported.

Mohamed Al Hammadi, CEO of ENEC, said: “All construction milestones for the Barakah Nuclear Energy Plant project have been achieved in accordance with the highest standards of quality and safety.

“The latest successful achievement of these milestones for Units 3 and 4, is a result of many months of hard work by all those involved.

“I am proud of our teams whose commitment and dedication is a key factor in the continued successful construction of the world’s largest nuclear new build construction site, with four identical units being built simultaneously.

“These milestones are a result of ENEC’s extensive collaboration with its prime contractor and joint venture partner, the Korean Electric Power Corporation (KEPCO).”

With the successful setting of Unit 3’s RCB Liner Dome section, it is now more than 62% complete and work to pour the concrete and complete the RCB is progressing steadily.

The RCB is expected to be completed in the first quarter of 2017, roughly a year after similar work was concluded on Unit 2, in line with ENEC’s construction schedule.

“The completion of the Turbine Generator Operating Deck and the setting of the final Reactor Containment Liner Plate Rings on Unit 4 has allowed work to begin on erecting the Turbine Building and the interior and exterior concrete for the Unit’s RCB is now being poured.

Once completed, we will be ready for the installation of Unit 4’s Reactor Pressure Vessel in mid-2017,” said Ahmed Al Rumaithi, ENEC’s Deputy CEO.

“The construction of Unit 4 is now 35% complete and is ahead of schedule, with the completion of the deck and rings having occurred roughly 10 months after similar work was concluded on Unit 3.”

The Barakah Nuclear Energy Plant is scheduled for completion in 2020, with construction having started in 2012.

Most popular

Awards

Construction industry conversations around digitisation must evolve
The Middle East construction industry’s approach to tech must evolve and focus on how can

Conferences

HKA: Volume of construction disputes to stay consistent in 2019
EXCLUSIVE: Consultancy’s Michael McSorley talks about methods to avoid and ‘speedily resolve’ construction disputes
Construction industry conversations around digitisation must evolve
The Middle East construction industry’s approach to tech must evolve and focus on how can

Latest Issue

Construction Week - Issue 751
Oct 13, 2019