Collaborating with local contractors, Musanada has fitted construction equipment with GPS devices to reduce material loss by 15% and achieve savings worth $0.25 per sqm

Abu Dhabi General Services Company (Musanada) revealed its implementation of global positioning system (GPS) devices in construction equipment has raised productivity by 30% and reduced material loss by 15%. 

Moreover, the technology achieves savings worth $0.25 (AED0.93) per sqm, after the device's total cost of supply and installation is factored in. 

The agency has deployed an engineering system based on machine guidance – which uses GPS devices – to carry out grading works. 

READ: Technology promises improved onsite health and safety

Musanada claims the move guarantees highly accurate control, improves the management of occupational safety at construction sites, and enhances work quality. 

The new system, being operation in collaboration with contracting companies, will allow Musanada to "stay abreast of [...] work-related developments, minimise the occurrence of occupational incidents, and help maintain life and property". 

Eng Suwaidan Rashed Al Dhaheri, acting CEO of Musanada, said the technology improves tasks such as excavation, levelling, and grading of roads' foundation layers.

READ: Construction Week Leaders in UAE 2015 – Is the GCC using construction tech?

He added: "Upgrading machines [for those activities] by deploying GPS control has helped increase productivity by 30%, which will help complete and deliver projects as per the defined schedule." 

The reduction of construction material loss is achieved by deviating from the traditional method of implementing the activities, which "relied on repeating the work in order to reach the required quality". 

A database can be built off the GPS system's self-memory, which "allows fast transfer of all positioning data to [computers, in order] to be analysed by relevant applications". 

No human intervention is required, except for an equipment operator that has been adequately trained to use the system effectively and efficiently, Al Dhaheri said.

READ: GCC construction needs a tech transformation

Excavation, levelling, and grading road foundations previously depended on "the skills and accumulated experience of the machine operator to complete the required work within the shortest possible time", he continued. 

Foremen and other site operatives were also required on site, "due to the operator's inadequate visibility to see around and under the machine", Al Dhaheri explained. 

According to WAM, he added: "The new system operates based on the installation of the machine guidance application, which allows real-time tracking of equipment and ensures that the earth level is matched to the levels and ratios pre-defined in the system.

"The objective we hope to achieve from the implementation of this system in terms of occupational health is minimising the presence of human resources during the movement of equipment inside operational areas, [thus] minimising the likelihood of fatal incidents or unsafe use of equipment." 

READ: Six must-have construction tech tools

Article Context: 
News
Story Relations: 
Musanada completes glass works at Al Ain Hospital
Abu Dhabi Airports signs MoU with Musanada
Al Ain: Musanada to complete four schools by April
Media Embed: 
Published Date: 
Tuesday, May 30, 2017 - 09:30
Parent Source id: 
0
Modified Date: 
Tuesday, May 30, 2017 - 09:30
Extra Data: 

[{"id":"269","name":"NEWS","parent":"0","menu":"1","UniqueName":"news"},{"id":"284","name":"PMV","parent":"-1","menu":"1","UniqueName":"pmv"},{"id":"280","name":"Projects","parent":"-1","menu":"1","UniqueName":"projects"},{"id":"22","name":"abu dhabi","parent":"0","menu":"0","UniqueName":"abu-dhabi"},{"id":"8978","name":"Abu Dhabi General Services Company","parent":"0","menu":"0","UniqueName":"abu-dhabi-general-services-company"},{"id":"38793","name":"abu dhabi technology","parent":"0","menu":"0","UniqueName":"abu-dhabi-technology"},{"id":"38795","name":"construction equipment tracker","parent":"0","menu":"0","UniqueName":"construction-equipment-tracker"},{"id":"16023","name":"construction tech","parent":"0","menu":"0","UniqueName":"construction-tech"},{"id":"15444","name":"construction technology","parent":"0","menu":"0","UniqueName":"construction-technology"},{"id":"38796","name":"equipment tracking","parent":"0","menu":"0","UniqueName":"equipment-tracking"},{"id":"426","name":"GPS","parent":"0","menu":"0","UniqueName":"gps"},{"id":"349","name":"musanada","parent":"0","menu":"0","UniqueName":"musanada"},{"id":"21466","name":"musanada abu dhabi","parent":"0","menu":"0","UniqueName":"musanada-abu-dhabi"},{"id":"18055","name":"musanada uae","parent":"0","menu":"0","UniqueName":"musanada-uae"},{"id":"38794","name":"technology uae","parent":"0","menu":"0","UniqueName":"technology-uae"}]

Company Relations: 

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week Middle East 11th Jan 2020
Jan 16, 2020