First substation at Dubai Expo 2020 site completed

Dubai Electricity and Water Authority (DEWA) has inaugurated the first 132/11 kV main substation for Dubai Expo 2020

Construction on the substation began in July 2015 at a total cost of $47m.
Construction on the substation began in July 2015 at a total cost of $47m.

Dubai Electricity and Water Authority (DEWA) has inaugurated the first 132/11 kV main substation for Dubai Expo 2020.

The authority completed Mobility, one of three 132/11 kV main substation at the Expo 2020 Dubai site, in January 2018. The substation has a conversion capacity of 150 MVA.

Construction on the substation began in July 2015 at a total cost of $47m (AED173m), comprising $22m (AED80m) for the plant and $25m (AED93.6m) for the 132kV cables.

READ: DEWA awards $300m contract for H-Station Phase 4

Mobility is one of the substations responsible for generating electricity for the Expo 2020 Dubai, along with Sustainability and Opportunity, which are currently under construction.  

All three substations, named after the three subthemes of the Expo, are being built at a total cost of 114m (AED420m).

HE Reem Al Hashimy, Minister of State for International Cooperation and director general and board representative on the higher committee of the EXPO 2020 Dubai, said: “Expo 2020 Dubai gives great importance to Sustainability, making it one of its three pillars, along with Mobility and Opportunity. Our partnership with Dubai Electricity and Water Authority (DEWA) supports our commitment for Expo 2020 to be sustainable during its six-month period, and beyond.

"From here, we decided to generate half of the energy that Expo 2020 will use from renewable energy sources. Thankfully, DEWA is building three substations located close to Expo site, called Mobility, Sustainability, and Opportunity,”

Sustainability, the second 132/11 kV main substation at the site, is 95% complete and is due to be inaugurated in February 2018.

With a conversion capacity of 150 MVA, the total cost of the project is $28m (AED103m), including AED83m for the plant and $5.4m (AED20m) for the 132kV cables.

The Opportunity 132/11 kV main substation at Expo 2020 Dubai is 91% complete and is also expected to be inaugurated in February 2018.

The total cost of the project is $39m (AED142m), comprising $23m (AED83m) for the plant, and $16m (AED59.7m) for the 132kV cables.

As the event’s first official sustainable energy partner, the authority has allocated $1.1bn (AED4.26bn) to support the infrastructure for electricity and water at Expo 2020.

DEWA aims to generate half of the energy to be used by the exhibition from clean and renewable energy sources, to promote sustainability, a key pillar of the exhibition.

The authority’s Mohammed bin Rashid Al Maktoum Solar Park will also provide Expo 2020 Dubai with a dedicated capacity of 400MW of electricity.

 HE Saeed Mohammed Al Tayer, MD & CEO of DEWA, added: “As part of our partnership with Expo 2020 Dubai, as the official Sustainable Energy Partner, we intend to speed up the completion of our projects to provide sustainable energy to the facilities of the World Expo 2020."

Additionally, DEWA is building a smart grid to become the first network in the world to provide the entire value chain of generation, transmission, and distribution systems to the Expo.

 

Most popular

Awards

Go for gold at the 15th Construction Week Awards in December 2019!
Winners will be crowned under 14 categories at a gala ceremony in Dubai – are

Conferences

Leaders in Construction UAE Summit returns in Sept 2019
Dubai conference to see top officials discuss the people, trends, and challenges that will power
Leaders Kuwait 2018: New Kuwait 2035 needs smart city-led contracts
Localisation and contract modernisation are essential for Kuwait's diversification strategy

Latest Issue

Construction Week - Issue 741
May 11, 2019