$117m Azizi Plaza to be delivered ahead of schedule

Azizi Developments expects to deliver its $117m (AED430m) Azizi Plaza serviced apartments project ahead of schedule in the second quarter of 2018

Azizi Plaza serviced apartments.
Azizi Plaza serviced apartments.

Azizi Developments expects to deliver its $117m (AED430m) Azizi Plaza serviced apartments project ahead of schedule in the second quarter of 2018.

Launched in October 2016, the project will offer a total of 434 fully serviced and furnished apartments comprised of 286 studios, with 46 one-bedroom units and 102 two-bedroom units.

Along with 873m2 of retail space, the project will offer amenities such as a pool, a spa, and a healthcare club.

READ: UAE's Mina by Azizi project due to complete ahead of schedule

Mirwais Azizi, chairman of Azizi Group, said: “Al Furjan is now being recognized as a highly sought-after residential destination and a prime location for investment, given its strategic location to the Expo2020 site.

“We are proud to offer a high concentration of its residential units with more than 2000 units completed and delivered by Azizi since 2006.

“Al Furjan’s communal vibe encourages a socially-integrated way of life, and the access provided to swimming pools, health centres, retail centres, cafes and restaurants, reinforces Al Furjan’s growing brand position in Dubai.”

READ: UAE's Azizi Aliyah Residences to complete in Q2 2018

Azizi has made similar announcements of earlier than expected project completion dates this year, including the Mina by Azizi development on Dubai's Palm Jumeirah, which is due for a Q3 2018 delivery.

Azizi Aliyah Residences, one of its first major sell out projects in Dubai Healthcare City, will also be delivered ahead of schedule.

Launched in October 2016, Azizi Aliyah Residences, which achieved a 100% record sales in a single day, will be delivered in the second quarter of this year, the developer said last month.

Azizi said it will continue its rapid pace of development in Dubai’s Al Furjan district this year as it readies seven projects for delivery in the first and second quarters of 2018.

A master planned community located between Dubai’s Sheikh Zayed Road and Mohammed bin Rashid Road, Al Furjan will feature homes, retail centres, landscaped gardens, and easy access to public transportation.

Most popular

Awards

CW Oman Awards 2020: Meet the winners
A round of the thirteen winning names at the Construction Week Oman Awards 2020 that

Conferences

Leaders UAE 2020: Building a sustainable, 'resilient' infra
AESG’s Phillipa Grant, Burohappold’s Farah Naz, and Samana's Imran Farooq on a sustainable built environment
CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this

Latest Issue

Construction Week - Issue 767
Sep 01, 2020