Built to inform

Sign up for the daily newsletters

No, Thank you

Unit 2 of UAE's Barakah Nuclear Plant passes heat testing

Emirates Nuclear Energy Corporation completed hot functional testing for the UAE nuclear plant's second unit, two months after Unit 1 was completed in March

Cold hydrostatic testing of Unit 2 at the Barakah Nuclear Energy Plant was completed in July 2017.
Cold hydrostatic testing of Unit 2 at the Barakah Nuclear Energy Plant was completed in July 2017.

Emirates Nuclear Energy Corporation (ENEC) has completed hot functional testing of Unit 2 at the Barakah Nuclear Energy Plant, five years after work began on the component in April 2013.

Incorporating “all lessons learned from the same test on Unit 1”, ENEC said it worked closely with Korea Electric Power Corporation (KEPCO), and under the observation of Federal Authority for Nuclear Regulation (FANR) – the UAE’s independent nuclear regulatory body – to achieve this “major milestone” for Unit 2.

The HFT activity lasts a number of weeks, consisting of almost 200 individual and integrated tests performed on major systems to check their performance under normal operational conditions, without the presence of nuclear fuel in the reactor.

READ: Construction completed on Unit 1 of UAE's Barakah Nuclear Energy Plant

As part of the test, the reactor’s systems experience, for the first time, an operational temperature of nearly 300°C, and operational pressure of more than 150kg per cm2, equivalent to an underwater depth of 1,500m.

Demonstrating its readiness to operate once the reactor starts up for normal operations, the turbine also span for the first time at its maximum speed of 1,500RPM.

Speaking on the results, Eng Mohamed Al Hammadi, ENEC's chief executive officer, said: “This most recent round of testing ensures that Unit 2’s systems and components are on track to reliably and safely perform their intended functions when the plant becomes operational.

“The pre-operational commissioning phase of a nuclear energy plant is a complex and critical step towards starting to operate the plant.”

READ: Unit 3 of Barakah Nuclear Energy Plant works progressing

KEPCO is the joint venture partner and prime contractor for the Barakah project, which will have in four units in total.

ENEC said the four Units are “progressing safely and steadily”, with the overall construction rate for all standing at more than 89% as of June 2018.  

Construction on Unit 1 began in 2012, before it completed in March this year.

It has already been handed over to Nawah Energy Company for preparation to operate, pending regulatory approval.

Most popular

Awards

CW Oman Awards 2019: Countdown begins for gala event in Muscat
The winners and highly commended entries of the eighth CW Oman Awards will be named

Conferences

Leaders Kuwait 2018: New Kuwait 2035 needs smart city-led contracts
Localisation and contract modernisation are essential for Kuwait's diversification strategy
Construction Week's Leaders Kuwait 2018 summit opens
Speakers from Kuwait's Supreme Council for Planning and Development and CSCEC ME are at today's

Latest Issue

Construction Week - Issue 734
Mar 21, 2019