Built to inform

Sign up for the daily newsletters

No, Thank you

Dubai's Museum of the Future on track for delivery

Steel work for the project is expected to finish in the next three months, BAM International told Construction Week

Dubai's Museum of the Future is due to complete on time [image: Tekla].
Dubai's Museum of the Future is due to complete on time [image: Tekla].

The construction of Dubai's Museum of the Future is at an advanced stage and the technically complex project is on track for completion.

Steelwork is expected to be substantially complete in the next three months, allowing plenty of time for mechanical, electrical, and plumbing (MEP) fit-outs, internal lining, and architectural finishes, which have already commenced, to gather momentum soon, a representative from project contractor BAM International told Construction Week. 

“We are nearly there, with approximately 90% of the concrete work done,” said Denis McNelis, engineering manager at BAM International, which is constructing one of the region's most intricately designed developments.

“All the podium levels [and] the core are done, and volume-wise, approximately 95% of the volume is poured. 

“Structural steelwork is more than 90% complete; we’ve just got to finish off the bit over the bridge, and [...] because it is one of the most complicated elements, it’s due to be completed in the next couple of months.”

VIDEO: How Dubai's Museum of the Future is engineered 

“Because of the construction sequencing, we have to finish the steel before we can [implement] concrete work on the higher levels, because we can’t put the weight on the building until we have a finished, closed structure.

“We are only able to pour concrete up to level four, and we still have levels five, six, and seven to [work on],” he explained. 

McNelis described the Museum of the Future as an “engineering marvel” and reiterated that BAM is on track to complete its scope for the project on time. Buro Happold is engaged as the project's lead consultant.

Designed by architectural firm Killa Design, the oval-shaped superstructure features an impressive steel and glass façade and Arabic poem about innovation woven into the exterior of the building. The calligraphy on the building is a major design feature.

BAM International, in collaboration with other project stakeholders, has employed advanced building information modelling (BIM) and 3D modelling technologies to support the delivery of the project.

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week Middle East 11th Jan 2020
Jan 16, 2020