VIDEO: Construction update on Oman's Duqm Refinery project

The project has recorded 21,206 manpower on-site so far, achieving a total of 43 million safe manhours

Oman's Duqm Refinery will be completed in 2022
Duqm Refinery
Oman's Duqm Refinery will be completed in 2022

Oman's Duqm Refinery project has recorded 55.2% overall progress as of March 2020. 

The project progress so far includes 2,92,591m3 of concrete poured; 2,034 civil piles driven; 22,455.5 tonnes of structural steel usage; installation of a 95,843m pipe, and 35,579.7 tonnes of tanks used. 

The project has recorded 21,206 manpower on-site so far, achieving a total of 43 million safe manhours. 

Recently, Oman's Port of Duqm, which is facilitating the construction for Duqm Refinery, received the SAL Heavy Lift vessel M.V.Anne Sofie for its project, marking a milestone in heavy lift cargo operation. 

Most popular

Awards

Deadline approaches for CW Oman Awards 2020 in Muscat
You have until 20 January to submit your nominations for the ninth edition of the

Conferences

CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this
CW In Focus | Leaders in Construction Summit UAE 2019
A roundup of Construction Week's annual summit that was held in Dubai this September

Latest Issue

Construction Week - Issue 765
Jun 29, 2020