Petrofac installs modular auxiliary boilers at Oman's Duqm Refinery

The boilers were fabricated in northern Milan and assembled in Venice to make their transportation to Marghera Port easier

The boilers are based on a 'Plug and Play' module.
LinkedIn/ Petrofac - MACCHI Boiler and Mammoet
The boilers are based on a 'Plug and Play' module.

London Stock Exchange-listed and Jersey-headquartered oil and gas contractor, Petrofac has installed three modular auxiliary boilers modules at the Duqm Refinery in Oman, located 600km south of Muscat.

Petrofac said that the boilers were fabricated and assembled in northern Italy, with the fabrication having been conducted in northern Milan and assembly in Venice.

The boilers were manufactured by MACCHI, operational division of Sofinter S.p.A., in Via Ramo dell’Azoto plant. MACCHI is a supplier of industrial and heat recovery boilers for the oil and gas and petrochemical sectors.

Speaking about the project, which was being carried out amid the COVID-10 pandemic, Roula Borhgi, project engineer at Petrofc, said: “It was a critical time in the manufacturing period.”

“When the lockdown happened we had almost all the components completed, 90% delivered to the vendor, and they were in the middle of assembling,” she added.

The boilers were fabricated and assembled during the COVID-19 pandemic [Image: LinkedIn/ Petrofac -  MACCHI Boiler and Mammoet]

Each boiler, which weighs over 550 tonnes, is now put in place. These are ‘plug and play’ modules that are ready for commissioning.

Explaining the modular element futher, Arun Kumar, engineer at Petrofac, said: “We have followed a modular concept for the three identical boilers — all components such as pressure parts, interconnecting piping, structural steel, instruments and cabling are prefabricated and assembled at the vendor’s workshop.”

“It’s called a Plug and Play module since the module is ready for commissioning as soon as installed.”

Meanwhile, Roula said: “The reason why the project management chose a modularised option was to meet our milestones and try to mitigate any unpredictable issues or changes that can occur during execution, COVID-19 proved our selection was correct.”

The boilers were dispatched from the Marghera Port in Venice [Image: LinkedIn/ Petrofac -  MACCHI Boiler and Mammoet]

Petrofac, in a joint venture with Samsung Engineering, are undertaking the engineering, procurement, and construction (EPC) Package 2 contract worth approximately $2bn (OMR769m).

The refinery’s Package 2 comprises the build-up of temporary site facilities, comprising warehouses and offices; in addition to fencing, excavations, and foundation works for the main substation and administration buildings.

Most popular

Awards

CW Oman Awards 2020: Meet the winners
A round of the thirteen winning names at the Construction Week Oman Awards 2020 that

Conferences

Leaders UAE 2020: Building a sustainable, 'resilient' infra
AESG’s Phillipa Grant, Burohappold’s Farah Naz, and Samana's Imran Farooq on a sustainable built environment
CW In Focus | Inside the Leaders in KSA Awards 2019 in Riyadh
Meet the winners in all 10 categories and learn more about Vision 2030 in this

Latest Issue

Construction Week - Issue 767
Sep 01, 2020