Construction reaches 61% at Mina by Azizi on Dubai's Palm Jumeirah

Blockwork and internal plastering on East Crescent project have exceeded 85% and 70%, Azizi Developments says

Dubai's Mina by Azizi homes.
Azizi Developments
Dubai's Mina by Azizi homes.

Construction on Azizi Developments’ Mina by Azizi project on Dubai’s Palm Jumeirah has passed the 61% mark, with blockwork and internal plastering respectively passing 85% and 70%. 

In a statement, the Dubai developer said heating, ventilating, and air-conditioning progress stood at roughly 50%, with work on tiling, swimming pools, façades, elevator installation, and overall finishes also “advancing swiftly”.

Located on the East Crescent of Palm Jumeirah, Mina by Azizi has a total gross floor area of 2.2ha.

More than 69% of Mina by Azizi’s total area is allocated for gardens, a children’s play area, a jogging track, and outdoor spaces.

In a statement, Farhad Azizi, Azizi Developments’ chief executive officer, said Mina by Azizi’s speedy construction was a testament to the developer’s “customer-first mindset and clear commitment to deliver on [its] promises”.

He added: “With our focus on transparency, we deliver timely updates to keep our customers well-informed at all times."

The news comes as Azizi Developments looks to hand over the 178-residence project – spread across 120 one-bedroom, 54 two-bedroom, and four penthouse units – by December 2019.

Most popular

Awards

New category open for consultancies at CW Awards 2019 in Dubai
Sub-Consultancy of the Year to be crowned for the first time at the gala ceremony

Conferences

Leaders UAE 2019: Pinsent Masons confirmed as Gold Sponsor
Law firm is among the major construction industry players confirmed as sponsors for Leaders UAE's
Leaders in Construction UAE Summit returns in Sept 2019
Dubai conference to see top officials discuss the people, trends, and challenges that will power

Latest Issue

Construction Week - Issue 746
Jul 20, 2019