

Built to inform
Sign up for the daily newsletters
Barakah
18 Nov 2018
Concrete works and heavy equipment lifting have been completed for all four project units
27 May 2018
Nawah Energy Company, the plant's operator, said it has "entered the next phase of preparations
27 Mar 2018
Unit 1 is now completing operational readiness operations, with the overall project having achieved 86%
04 Jan 2018
Units 3 and 4 of the plant have been connected to the UAE's electricity transmission
03 Dec 2017
The nuclear energy facility's Unit 1 is 96% complete, with overall project completion established at
26 Jul 2017
Cold hydrostatic testing is conducted to ensure that components of the reactor coolant system and
08 Feb 2017
The final condenser for the nuclear energy project was recently fitted at its Unit 4,
25 Sep 2016
The CEO of Emirates Nuclear Energy Corporation (ENEC) said the project's rapid construction progress is
- 1 of 3
- ››