Barakah Nuclear Energy Plant

ENEC completes CHT test for Unit 4 at Barakah Nuclear Energy Plant
The CHT test verified the welds, joints, pipes, reactor coolant components, and highlighted the quality
ENEC completes fuel assembly loading into Unit 1 at Barakah
Following the safe completion of fuel assemblies loading, Nawah Energy Company and Kepco will start
Barakah Nuclear Energy Plant clears operational readiness assessment
ENEC and its subsidiary Nawah have announced that Unit 1 of Abu Dhabi’s Barakah Nuclear
ENEC hits 75m safe manhours at Barakah Nuclear Energy Plant
ENEC has completed more than 93% in the overall construction of 4 identical nuclear energy
Fanr board reviews Barakah Nuclear Energy Plant in Abu Dhabi
Federal Authority for Nuclear Regulation reviews progress on energy megaproject in Abu Dhabi's Al Dhafra
Enec's Barakah One Co, Kepco ink MoU for 'Barakah Model' projects
Agreement signed to further collaboration on investment, licensing, operations, and training in new nuclear energy
Construction of UAE's Barakah Nuclear Energy Plant reaches 93%
Enec confirms progress on Unit 3's energisation, marking milestone in Barakah NEP's testing and commissioning
Inside FANR's 2018 tests at UAE's Barakah NEP with Enec, Nawah
Federal regulator's 2018 report reveals key measures taken to ensure Barakah Nuclear Energy Plant's safety

Most popular

Latest Issue

Construction Week - Issue 765